S
Scott
I have not had problems with this in past projects, but obviously have it now.
I want to set a duration to 10days and have it only count 'working days'
(monday through Friday) in calculating the end date and the Start date
(especially, when their is a predecessor).
ie. Task 1 ends on a Friday. I want task 2 to be linked to task 1 and be
10 days in duration. Currently task 2 starts on a Saturday. How do I get
Task 2 to start on the following work day (ie. Monday).
I want the duration of the number of days or weeks to only count working
days!!!
Please help.
Thanks,
Scott
I want to set a duration to 10days and have it only count 'working days'
(monday through Friday) in calculating the end date and the Start date
(especially, when their is a predecessor).
ie. Task 1 ends on a Friday. I want task 2 to be linked to task 1 and be
10 days in duration. Currently task 2 starts on a Saturday. How do I get
Task 2 to start on the following work day (ie. Monday).
I want the duration of the number of days or weeks to only count working
days!!!
Please help.
Thanks,
Scott