D
Doug
I have a project whose tasks total 600 hours. Of the 600 hours there are
tasks and sub-tasks. If I add multiple resources (let's say 3 resources) for
each task, the duration for each task shows 1/3 of the time of the total
task. (i.e. a task estimated at 30 hours will show a duration of 10 hours
after adding 3 resources at 100%). Project will also pull in the finish dates
reflecting 10 hours of work instead of 30 (which is fine).
How can I get Project to continue to reflect the actual total number of
hours of effort (in this case 600) with multiple resources performing each
task? My objective is to show that the project requires 600 hours of effort,
but will not require 600 consecutive hours for completion.
Thanks.
tasks and sub-tasks. If I add multiple resources (let's say 3 resources) for
each task, the duration for each task shows 1/3 of the time of the total
task. (i.e. a task estimated at 30 hours will show a duration of 10 hours
after adding 3 resources at 100%). Project will also pull in the finish dates
reflecting 10 hours of work instead of 30 (which is fine).
How can I get Project to continue to reflect the actual total number of
hours of effort (in this case 600) with multiple resources performing each
task? My objective is to show that the project requires 600 hours of effort,
but will not require 600 consecutive hours for completion.
Thanks.