P
PaulPW
I've been struggling with this one all day, trying different things out and
scouring the web for an answer. Hopefully someone out there smarter than I
am is willing to help me out!
I have a few effort-driven FS dependant tasks in a section of my project.
They are phases of a demolition job, with a resource assigned (a contractor).
I have inserted a task for another resource (equipment) - a dumpster for the
demolition debris. The duration of the dumpster task needs to cover the
entire duration of the other tasks - I do NOT want to set the duration or the
dates manually, but let Project calculate when and how long as it needs to
be. This will help me plan when to order the dumpster & for how long.
The duration says "1 day?" since I have not specified it.
I have tried various SS & FF relationships:
With SS as the successor (i.e. "demolition can't start unless the dumpster
is there"), Project puts the dumpster task starting right at the beginning of
my project (since there are no predecessors).
With FF as the predecessor (i.e. "dumpster task cannot be removed until
demolition finishes"), Project places the dumpster at the end of the
demolition task, BUT the duration is only one day!
In fact, both of these SS & FF statements are true, but Project will not
allow me to enter the same task # as SS successor & FF predecessor. I tried
it with SS on the first demolition task and FF on the last, but that kicked
up a circular reference error.
Any ideas? I'm sure it must have something to do with resources that I am
getting wrong.
Sorry this is such long explanation.
Paul
scouring the web for an answer. Hopefully someone out there smarter than I
am is willing to help me out!
I have a few effort-driven FS dependant tasks in a section of my project.
They are phases of a demolition job, with a resource assigned (a contractor).
I have inserted a task for another resource (equipment) - a dumpster for the
demolition debris. The duration of the dumpster task needs to cover the
entire duration of the other tasks - I do NOT want to set the duration or the
dates manually, but let Project calculate when and how long as it needs to
be. This will help me plan when to order the dumpster & for how long.
The duration says "1 day?" since I have not specified it.
I have tried various SS & FF relationships:
With SS as the successor (i.e. "demolition can't start unless the dumpster
is there"), Project puts the dumpster task starting right at the beginning of
my project (since there are no predecessors).
With FF as the predecessor (i.e. "dumpster task cannot be removed until
demolition finishes"), Project places the dumpster at the end of the
demolition task, BUT the duration is only one day!
In fact, both of these SS & FF statements are true, but Project will not
allow me to enter the same task # as SS successor & FF predecessor. I tried
it with SS on the first demolition task and FF on the last, but that kicked
up a circular reference error.
Any ideas? I'm sure it must have something to do with resources that I am
getting wrong.
Sorry this is such long explanation.
Paul