R
ronjon
i there a way to have ms project automatically recalculate task units on
tasks with SS and FF dependencies when duration changes? eg.
task A: go fish in lake
task B: collect fish
task C: prepare fish for dinner
task D: oversee whole fising
my task A,B,C are dependent on finish - start.
Task D has a dependency SS on task A and FF on task C.
whenever task C finished later than planned i need to have task D
automatically reschedule the end date the same as task C, still leaving
the startdate SS on task A.
whenever i tried this now in project (set the double dependency) my
whole task D shifts date, leaving the amount of work, units and duration
the same.
tasks with SS and FF dependencies when duration changes? eg.
task A: go fish in lake
task B: collect fish
task C: prepare fish for dinner
task D: oversee whole fising
my task A,B,C are dependent on finish - start.
Task D has a dependency SS on task A and FF on task C.
whenever task C finished later than planned i need to have task D
automatically reschedule the end date the same as task C, still leaving
the startdate SS on task A.
whenever i tried this now in project (set the double dependency) my
whole task D shifts date, leaving the amount of work, units and duration
the same.