F
Frustrated Kiwi
Hi
I'm struggling with project, What I want to do seems very basic, but it just
doesn't seem to do it
I need to have the start of a task linked to one task and the end linked to
another task. The duration is to be determined by the other 2 tasks, not
resources or an entered duration. I'm not assigning resources at all, so
they wont effect it.
I can do this by having 2 sub tasks, one being the start date and one the
end date, but that means I need 3 lines to tell a pretty simple story, I have
to change the Bar style and roll up the task to make it look like one task
not 3 when printing.
Surely there's an easyer way to do it in one task. (I have used links from
Excel to calculate the duration, but that adds an even more work)
Your help is appreciated
I'm struggling with project, What I want to do seems very basic, but it just
doesn't seem to do it
I need to have the start of a task linked to one task and the end linked to
another task. The duration is to be determined by the other 2 tasks, not
resources or an entered duration. I'm not assigning resources at all, so
they wont effect it.
I can do this by having 2 sub tasks, one being the start date and one the
end date, but that means I need 3 lines to tell a pretty simple story, I have
to change the Bar style and roll up the task to make it look like one task
not 3 when printing.
Surely there's an easyer way to do it in one task. (I have used links from
Excel to calculate the duration, but that adds an even more work)
Your help is appreciated