NK said:
Mike,
The problem that I am having is that the numbers don't add up. If you add
up the time for the subtasks. it is not equal to the total time of the
entire summary task, even when you look at the times and dates for the task.
Is there anyway of breaking tasks into hourly segments or will that not work?
Nick
Nick,
Mike explained how Duration of a Summary Line is calculated by Project.
However, I note in your second post that you are talking about "time".
Perhaps you are looking at the Work field and the Work field of a
Summary Line WILL equal the sum of Work for all subtasks - unless
Calculation (Tools/Options/Calculation tab) is set to manual.
Duration time and Work time are two different entities in Project.
Duration is the time (normally in days) during which a task will/needs
to be accomplished. Conversely, Work time is the effort by one or more
resources to actually perform the task. Depending on how resources are
assigned, the two values (minutes, hours, days, etc.) may or may not be
equal.
If we still are not "getting it", please elaborate so we can give you
the answer you need (although it may not be the answer you want or
expect). For example, what "numbers" don't add up?
Hope this helps.
John
Project MVP