Just remember to set the task's duration to 40 hours, NOT 60 hours,
when
you enter it. The starting duration is the time required to do the work,
not the total amount of the work. Since you're estimating 60 hours
already as you start the process, it's no big deal to prorate it yourself
between the two resources according the way you'd like them to do it.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Thanks for the quick answers.
I can know tell my co-workers that it can't be done automatically and
that it is not my lack of knowledge ;-).
I will advise my co-workers two work with the split screen option to make
manual adjustments.
Wesley
Try the split screen method that I suggested, assigning the first
resource to do 40 hours at 100% and the second to do 20 hours @ 100%, it
will work and I checked it just now to make sure. You're right on
the
resource assignment toolbar button, it does still split it 30/30 -
should have double checked it before typing - sorry, my bad.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Thanks for you're suggestions, but they did nog solve my problem, when
I assign two resources at once it still divides 60 hours equaly (30/30)
among the two resources and finishes in 5,5 day's.
I will try to be more specific/clear.
The only thing a know is that I have 60 hours for a task (fixed price).
Then I assign two resources with different calenders (on 40 hours
and
one 20 hours a week) to this task and I want Project to finish the task
As Soon As Possible. So Project should calculate/see that it can finish
in 5 day's. I don't want to set the duration myself or assign a
specific amount of hours to a resource, because that's impossible if
you have more difficult calenders, hours to spend and resources on one
task.
I hope I'm clear about what I want, but I also added an attachment with
some additional information/visualisation.
Wesley
message This is where I'd split the screen in the Gantt chart to make the
assignments. Select the task. In the bottom window click in the
resource
column and add the full-time resource, 100%, 40 hours work. In the
next
line add the part-time resource, 100%, 20 hours work. Now click
the
"OK"
button.
Or if you prefer to use the regular Assign Resources dialog, remember
that
100% for your 4 hour a day resource is 4 hours per day. Enter the
task in
the task list with a 5 days duration. Open the Assign Resource,
select Joe
Fulltimer, hold down control and select Betty Partimer, and click the
"Assign" button. Make sure you assign them both at once, not
consecutively.
It should leave the duration at 5 days, assign both resources @ 100%,
with
one doing 40 hours work and the other at 20 hours work.
The inital task duration should be 5 days or 40 hours, BTW, not 60.
Don't
mix up duration estimates with work estimates when you initially enter
the
task and its expected duration in the Gantt chart task list.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hello,
I hope someone can help me with the following problem.
* When I assign one resource (A) with a normal (40 hour) calender to
a
task of 60 hours it will take 7,5 day's to finish it.
* When I assign one resource (B) with a 20hour calender to a task of
60
hours it will take 15 day's to finish it.
So far so good, but when I assign both resources to the task it still
takes 7,5 day's to finish it, because project divides the work
between the
two resources (both 30 hours of work).
But I want project to schedule the task (automatically) in a way that
task
finishes in 5 day's. That is possible when project assigns 40
hours
of
work to resoure A and 20 hours to resource B.
Wesley
PS I know that I can adjust hours in the Resource Usage screen,
but I
want
Project to do it by default.