K
Kettlewell
Hi.
2 scenarios (might be same answer)
1) I have a task with 2 sub tasks. Each sub task is 2 hours long.
Task displays 202 hours (I expect 4). because each of my sub tasks is
about a month apart, the task is showing from start time to finish
time. How do I get my 4 hours to show up.... partly for visual, and
partly it kills my resources.
2) Recurring tasks... 1 task per month for 1 hour duration, I expect
only 12 hours of resource duration, but is showing as 1881 hours
How do I get the actual hours to show, and not the start to finish
date times?
Thanks
Matt Kettlewell
Kettlewell Enterprises, Inc
2 scenarios (might be same answer)
1) I have a task with 2 sub tasks. Each sub task is 2 hours long.
Task displays 202 hours (I expect 4). because each of my sub tasks is
about a month apart, the task is showing from start time to finish
time. How do I get my 4 hours to show up.... partly for visual, and
partly it kills my resources.
2) Recurring tasks... 1 task per month for 1 hour duration, I expect
only 12 hours of resource duration, but is showing as 1881 hours
How do I get the actual hours to show, and not the start to finish
date times?
Thanks
Matt Kettlewell
Kettlewell Enterprises, Inc