G
GreenMonster
If I have a task "Order Materials" and the time it takes for the materials
to arrive, once ordered, is 30 days, would it be correct to set my task
duration to 30 days even though the actual ordering of the materials takes a
few minutes?
The resources for the task are all "material" resources, no "work"
resources.
to arrive, once ordered, is 30 days, would it be correct to set my task
duration to 30 days even though the actual ordering of the materials takes a
few minutes?
The resources for the task are all "material" resources, no "work"
resources.