A
Anna
When I link a predecessor task to a task under a subtask, the subtask
duration calculation shows an incorrect calculation. For example, prior to
linking, the subtask shows 2 hours but as soon as I link to a task in another
grouping - the subtask total updates to show 10 hours. It always updates to
show a very high duration. This started last night when I changed my
schedule to be a 24 hour schedule and am wondering if that somehow created a
constraint with a resource?
duration calculation shows an incorrect calculation. For example, prior to
linking, the subtask shows 2 hours but as soon as I link to a task in another
grouping - the subtask total updates to show 10 hours. It always updates to
show a very high duration. This started last night when I changed my
schedule to be a 24 hour schedule and am wondering if that somehow created a
constraint with a resource?