S
Shahriar N k
Is there any way to not include lag time in the duration value for summary
tasks?
Here is some more detail:
My projects are IT projects.
A QA(quality assurance) person can test a task after a D(developer)
completes his task. But QA testing occours the day after D finishes work. So,
if D finishes
today QA will test tomorrow.
To schedule such a situation, i have made D(task) predecessor of QA (task)
with one day lag time.
But this lag time shows in the total time(duration) of the summary task. in
other
words the summary task duration also has this lag time - which i dont want.
so, is there any way to make the summary task ignore the lag(/lead) time in
its subtasks?
Eagerly waiting for your reply.
thank you.
tasks?
Here is some more detail:
My projects are IT projects.
A QA(quality assurance) person can test a task after a D(developer)
completes his task. But QA testing occours the day after D finishes work. So,
if D finishes
today QA will test tomorrow.
To schedule such a situation, i have made D(task) predecessor of QA (task)
with one day lag time.
But this lag time shows in the total time(duration) of the summary task. in
other
words the summary task duration also has this lag time - which i dont want.
so, is there any way to make the summary task ignore the lag(/lead) time in
its subtasks?
Eagerly waiting for your reply.
thank you.