The summary task duration extends from the start date and time of the first
milestone to the end date and time of the last milestone. That's implicit
in the definition of "duration." Durations are not additive in a summary
task regardless of whether the subtasks are performance tasks or milestones.
Durations are always computed in minutes. If the earliest and latest
milestones don't happen to occur at exactly the start or end of a workday,
the number of working minutes between them will calculate out to some
decimal fraction when divided by the hours in a day in order to convert them
to workdays for display on your task table.
FYI, a task list that consists of nothing but milestones is useless for
scheduling work or monitoring progress and budget. From what you describe
as to what you have right now, you don't have project plans at all - you
have to-do lists outlining the goals you hope to achieve but there's nothing
there to actually help you organize and direct the work so you can manage to
achieve them. You're still flying as blind as you'd be if you weren't using
Project at all.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Sara Miller said:
I have a Summary Task call "Inputs" with multiple subtasks all of which are
milestones (duration = zero days). Each of these has an external
predecessor
link to multiple subprojects. The tasks to which they are linked are also
milestones. In all cases the resource field is not used.
Why does the duration in the Inputs Summary task have a fraction of a day
(648.25 days)? All of the subtasks are zero day milestones.