Hi redmadcap,
Is there a resource assigned to the task and the resource's calendar
working time is different from the project calendar?
It's fairly easy to create a situation where the duration of a
summary task is different from subtask durations when resources with
different working time definitions are involved.
For example:
Two tasks linked F to S both with 5 hours duration. The project
calendar is the "standard" 8:00 am to 12:00 and 13:00 pm to 17:00.
When no resources are assigned, the summary task duration shows 10
hours.
Task A's schedule: Oct 13 08:00 to Oct 13 14:00
Task B's schedule: Oct 13 14:00 to Oct 14 10:00
Create a resource whose working time definition is 08:00 to 12:00
and 13:00 to 19:00 - or 10 working hours per day. After assigning
the resource:
Task A's schedule: Oct 13 08:00 to Oct 13 14:00
Task B's schedule: Oct 13 14:00 to Oct 13 19:00
The summary task duration changes to 8 hours. The two additional
hours that the resource works from 17:00 to 19:00 are not working
time on the project calendar. Because no resources are assigned to
the summary task, it is the project calendar's working definition of
08:00 to 17:00 that project uses when it shows the duration. The
amount of work on the task is correct -- 10 hours.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"redmadcap" wrote in message news:
[email protected]...