Tom
Durations that I had set for each task has changed after I assigned work
hours to the task. Example: before assigning work hours, task A = 3days.
After assigning 4 hours of work to Task A, duration is now 2.94days. I am a
novice user. My understanding of work and duration is: duration is length of
time for a task to get completed, work is the actual amount of time for a
resource to complete task. For example, it may take a few days of phone-tag
to get someone on the phone for a conversation that only lasts a few minutes.
So duration would be the required number of days and the work would be the
time it took to completeion each call attempt.
Question is: Does assigning work hours to task change the duration? And, is
my understanding of work and duration correct?
hours to the task. Example: before assigning work hours, task A = 3days.
After assigning 4 hours of work to Task A, duration is now 2.94days. I am a
novice user. My understanding of work and duration is: duration is length of
time for a task to get completed, work is the actual amount of time for a
resource to complete task. For example, it may take a few days of phone-tag
to get someone on the phone for a conversation that only lasts a few minutes.
So duration would be the required number of days and the work would be the
time it took to completeion each call attempt.
Question is: Does assigning work hours to task change the duration? And, is
my understanding of work and duration correct?