I have months as the duration units but the predecessor column calculates in
hours. How do I change to months?

Thanks and
 
J

Jack Dahlgren

The predecessor column is not calculating in hours. It is displaying in
hours. It is really calculating in minutes.

I don't believe that there is any way to change how it displays. Months have
a varying number of hours so they are not a very precise unit which is why
Project generally avoids displaying them. Sorry.

-Jack
 
S

Steve House

The predecessor column? That displays the task number(s) of the predecessor
of the task in question. It's not any unit of time except when lag or lead
times are part of the link type, as in "FS+3d."
 