How many resources will you have? If it's just one resource, that means
that over the course of 2 working weeks or 80 working hours he will do 20
man-hours of work. That corresponds to a resource assignment percentage of
20/80 or 25%. If you have 2 resources to assign, 20 man-hours effort gets
distributed between them (unless you override it) so that means that over
the course of 80 duration hours each resource does 10 man-hours of work,
equivalent to being assigned at an assignment level of 12.5%.
Enter your task and set its duration to 2 weeks. Assign your resources at
the appropriate level in a single operation. Or if you prefer make the task
non-effort driven and you can assign the resources either both at the same
time or one after the other as you choose. If you want to adjust either the
resource percentage or the resource man-hours afterwards, set the task type
to "fixed duration." That way editing the percentage recalculate the work
while editing the work recalculates the percentage but in either case,
duration will stay constant at 2 weeks. Note that if there is more than one
resource involved, adding or removing a body will change duration regardless
of task type if the task is effort driven.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs