S
Simon
How can I show the length of time for a task without streching the duration.
I have a task of 200 hours, resourced at 50%. My project keeps showing the
duration as a 25 days block, and not streched over the 50 days the resource
level gives. The only way I have been able to show an acurate job length is
to increase the duration to 50 days.
I have a task of 200 hours, resourced at 50%. My project keeps showing the
duration as a 25 days block, and not streched over the 50 days the resource
level gives. The only way I have been able to show an acurate job length is
to increase the duration to 50 days.