% Complete based on resource

P

PhilosophersSage

I am still very new to project 2003 and am trying to figure out how to level
% Complete based on resource and duration vs. just duration for example
Project currently shows this:
Resource Duration % Comp
Task 25
Sub task 1 800% 2days 0
Sub task 2 400% 1day 100
Sub task 3 800% 1day 0
Would like it to show:
Resource Duration % Comp
Task 14
Sub task 1 800% 2days 0
Sub task 2 400% 1day 100
Sub task 3 800% 1day 0

Sub task 2 is 14% of overall work but 25% of total duration how do I show
actual work? Thanks for the help!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top