I am still very new to project 2003 and am trying to figure out how to level
% Complete based on resource and duration vs. just duration for example
Project currently shows this:
Resource Duration % Comp
Task 25
Sub task 1 800% 2days 0
Sub task 2 400% 1day 100
Sub task 3 800% 1day 0
Would like it to show:
Resource Duration % Comp
Task 14
Sub task 1 800% 2days 0
Sub task 2 400% 1day 100
Sub task 3 800% 1day 0
Sub task 2 is 14% of overall work but 25% of total duration how do I show
actual work? Thanks for the help!
% Complete based on resource and duration vs. just duration for example
Project currently shows this:
Resource Duration % Comp
Task 25
Sub task 1 800% 2days 0
Sub task 2 400% 1day 100
Sub task 3 800% 1day 0
Would like it to show:
Resource Duration % Comp
Task 14
Sub task 1 800% 2days 0
Sub task 2 400% 1day 100
Sub task 3 800% 1day 0
Sub task 2 is 14% of overall work but 25% of total duration how do I show
actual work? Thanks for the help!