B
bam
Question;
(1) I entered duration for tasks
(2) I displayed the work column.
(3) I noticed that duration and work were equal.
Then I
(4) modified the calendar work days for various resources -- showing some
available for two days a week, three days a week, etc.
(5) The duration and effort values are still the same for all resources --
shouldn't duration be generally more than effort?
Thanks in advance.
bmac
(1) I entered duration for tasks
(2) I displayed the work column.
(3) I noticed that duration and work were equal.
Then I
(4) modified the calendar work days for various resources -- showing some
available for two days a week, three days a week, etc.
(5) The duration and effort values are still the same for all resources --
shouldn't duration be generally more than effort?
Thanks in advance.
bmac