Duration

W

whatzzup

How does the duration in Baseline get automatically incremented to reflect
the baseline start and finish date? Thanks all
 
J

JulieS

Hi Whatzzup,

When you save a baseline the baseline start and baseline finish dates are
saved as is the baseline duration. To see the baseline data after you have
saved a baseline, apply the baseline table. (View > Table > More Tables and
select the baseline table.

Hope this helps. Let us know how you get along.

Julie
 
S

Steve House [Project MVP]

The baseline doesn't get automatically updated - that's the whole idea of a
baseline. When you have completed planning and are about to start work, you
save the baseline. This takes a "snapshot" that locks down and preserves
your original plan. Now when you enter actual progress into the plan you'll
find start and end dates for the tasks you've worked and their dependents
change to reflect the actuals you have obtained. But the *baseline* OTOH
does *not* update , thus giving you a constant reference against which you
can compare the project as it currently stands against what you thought
you'd have by this date, giving you variances etc to determine if you're
running ahead or behind schedule and over or under budget.
 