During

T

totalnewbie

I'm using only full days for scheduling (i.e., not hours), yet the duration
caclucation is coming back in partial days. Why?
 
S

Steve House [Project MVP]

Duration is always stored and computed to the minute by Project. The
ability enter and display durations in days, weeks, etc, is there only for
convenience. Fractions of a day in the displayed duration will result
whenever a calculation happens to come out to something other than an
integer multiple of the "hours per day" setting.
 