Dynamic duration of task

G

GreatDane

I have a project, where tree task depends on each other. The first is on
fixed dates, and the last is in fixed duration, but can be moved dependent on
when other task finish.

The second task is a maintenance task, with a fixed resources use every week.

How do I make the second task automatically fill out the time between the
two other tasks? This is important in order to get the used resources right.




Thanks in advance


GreatDane
 
P

Peter Hulse

What you want is a hammock task, which MSP doesn't support. These will
stretch or shrink as preceding and succeeding tasks move around. Help create
the demand for the next upgrade!
 
J

Joe

Peter is incorrect. MSP does support hammock task and you can create and use
them in this situation.
 