"e days" estimated or elapsed duration does not show up in summary

S

StaciW

When entering estimated durations in sub-tasks, summary line does not display
task as e-day.

Are summary tasks 'capable' of displaying estimated duration tasks or will
they default to a non-estimated duration?
 
J

Jan De Messemaeker

Hi,

e-days mean elapsed days (ignoring the calndar) and not estimated days.
Does that help?
 
S

StaciW

Thanks for the response. What I am actually asking is whether or not the
summary line will show the same value as the sub-task.

If the subtask is (4ed) the summary line shows (4d) - for what I have seen.

Is there anyway to enable the summary line to show it as an elapsed duration
event or does it simply show the duration regardless of how each subtask is
provisioned?

Thank you!
 
J

Jan De Messemaeker

Hi,

Duration of a summary line is shown as is selected in Tools, Options,
Schedule, Duration is shown in...
HTH
 
D

DavidC

Hi,

The summary task calculates its duration based on the hours per day, days
per week and weeks per month set in Options calendar. Since the tasks may
have a diffeerent calendar to the project calendar then yes the summary task
may well have a different duration to the of the underlying tasks. The
summary task is merely looking at the earliest of the start times forthe
underlying tasks, and the
latest of the finish times of the underlying tasks and then calculating the
duration based on the difference between that start and finsh and as defined
under the options. The underlying tasks might say all be five day tasks on
a five day calendar (set under Change working time) and show 'correctly the
five day task spanning from Wednesday to Tuesday, the Summary Task will also
show start on Wednesday and Finsh on Tuesday, but since the options are set
for a seven day week, then the duration will show as seven days not five.
Hence the confusion that can arise.

Definately a little 'trap' to be aware of, especially when people see the
differences between the task durations and the summary task duration.

Hope this helps
 
S

StaciW

Mike - that is what I expected, thanks for the straight on this one!

___________
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top