EAC

C

Chris

I can export into Excel time-phased data for BAC and plot a baseline cost expenditure over time. Why isn't EAC available as an export field so I can plot it agaist time to produce a standard s-curve?

I want to show forecast expenditure to the final Estimate at Completion - surely there is a way of doing this?
 
M

Mark Durrenberger

EAC (estimate at complete) get's recomputed each time you recorde actuals
(ACWP) and Earned (BCWP)

Mark

--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________

The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.

- Sir John Harvey-Jones
Chris said:
I can export into Excel time-phased data for BAC and plot a baseline cost
expenditure over time. Why isn't EAC available as an export field so I can
plot it agaist time to produce a standard s-curve?
I want to show forecast expenditure to the final Estimate at Completion -
surely there is a way of doing this?
 