S
Steve Barlow (UK)
I have three tasks A1, A2 and B. A1 and A2 have different start and finish
dates and ideally different durations. A1 and A2 are NOT dependent on each
other but B is dependent on them both.
I want B to start whichever of A1 and A2 finish first. However, the default
linkage for FS uses the latest of the two finishes. I’ve also tried
variations on SS and adding a lag the same as the A1 & A2 durations but
similar (too late) result.
Can’t help but think the answer is staring me in the face and that I’m not
applying the correct logic. Can any one offer any thoughts please?
Regards
Steve B
dates and ideally different durations. A1 and A2 are NOT dependent on each
other but B is dependent on them both.
I want B to start whichever of A1 and A2 finish first. However, the default
linkage for FS uses the latest of the two finishes. I’ve also tried
variations on SS and adding a lag the same as the A1 & A2 durations but
similar (too late) result.
Can’t help but think the answer is staring me in the face and that I’m not
applying the correct logic. Can any one offer any thoughts please?
Regards
Steve B