K
KingKikapu
I know it's generally considered bad form to link a predecessor b
negative lag (ex: FS - 1day), so I try to go from the other end (ex: S
+ 5 days).
I have a problem though: what if I have a task that is expected to b
split in work (let's say 4 days then split for a while, then another
days of work), and I want to schedule a successor that will wait until
days of ACTUAL work are done until it starts. Does project know th
difference between 5 days lag and 5 days of work lag
negative lag (ex: FS - 1day), so I try to go from the other end (ex: S
+ 5 days).
I have a problem though: what if I have a task that is expected to b
split in work (let's say 4 days then split for a while, then another
days of work), and I want to schedule a successor that will wait until
days of ACTUAL work are done until it starts. Does project know th
difference between 5 days lag and 5 days of work lag