W
Wilson
I'm trying to identify metrics that the PMO can use to control this project
and I'm having difficulty because the planning team decided to not input cost
or resource information. They have simply assigned responsibilities via a
text field and manage the cost aspect somewhere else. The PMO is looking for
"EVM" type metrics but without cost and resource info I'm sort of at a loss.
Is it possible and or does it even make sense to jimmy the EVM metrics to use
only duration? I.e. Instead of using BCWP - BCWS, use # of Activities
completed - # of Activities scheduled to be completed.... Another example I
considered was a modified Earned Schedule (*we started the project in Feb):
(# of months complete) + {[(# of tasks completed)-(# of tasks scheduled
through April)] / [(# of tasks scheduled in May)-((# of tasks scheduled
through April)]}
Using the data from the above formula, I would then be able to arrive at
SPI(t) & SV(t)
QUESTION - Does this make any sense (considering the limited amount of data
I have to work with) or am I crazy?
and I'm having difficulty because the planning team decided to not input cost
or resource information. They have simply assigned responsibilities via a
text field and manage the cost aspect somewhere else. The PMO is looking for
"EVM" type metrics but without cost and resource info I'm sort of at a loss.
Is it possible and or does it even make sense to jimmy the EVM metrics to use
only duration? I.e. Instead of using BCWP - BCWS, use # of Activities
completed - # of Activities scheduled to be completed.... Another example I
considered was a modified Earned Schedule (*we started the project in Feb):
(# of months complete) + {[(# of tasks completed)-(# of tasks scheduled
through April)] / [(# of tasks scheduled in May)-((# of tasks scheduled
through April)]}
Using the data from the above formula, I would then be able to arrive at
SPI(t) & SV(t)
QUESTION - Does this make any sense (considering the limited amount of data
I have to work with) or am I crazy?