S
Shawn
I am using Project 2003. For the sake of EV Analysis I have changed the
Calculation tab in Options and checked mark all relevant options for EV
Analysis.
Here is the problem.
there is a task which has been scheduled before status date and the budget
is $820. Once I change the %complete from 0% to 50%, Project calculates BCWS
for $820 (which is right), however, BCWP shows $570 which is incorrect. BCWP
must be equal to %50 of $820 which is $410.
By the way there are another tasks with almost the same situation and BCWP
is being calculated properly. I was wondering what can make this
miscalculation by Project. Thank you for your help in advance.
Calculation tab in Options and checked mark all relevant options for EV
Analysis.
Here is the problem.
there is a task which has been scheduled before status date and the budget
is $820. Once I change the %complete from 0% to 50%, Project calculates BCWS
for $820 (which is right), however, BCWP shows $570 which is incorrect. BCWP
must be equal to %50 of $820 which is $410.
By the way there are another tasks with almost the same situation and BCWP
is being calculated properly. I was wondering what can make this
miscalculation by Project. Thank you for your help in advance.