Earned value

A

AmitB

I have baselined my plan and set a resource rate of $1.00/hr
As I track the plan and enter actuals, i see the ACWP numbers, but the BCWP
and BCWS numbers are stuck at zero. I've tried changing the status data from
NA to dates both in the past and in the future, but BCWP and BCWS are still
zero for tasks that have even been completed. What am i doing wrong ?
 
A

AmitB

Thanks Jack, you were bang on ! Should have asked earlier and saved myself 2
hours of agony. Will proceed to rating the reply.
 