V
viny
if i have task of 4day duration,it starts on 1jul & ends on 4jul & resource
to it is 2labour at Rs 100/d.when i track it on 3jul it is delayed in start
by 1day & %complete is 25%.if i see BCWP earned value on jul3 it should show
me rs.200. but if u see according to status date it gives rs.600/- at 3jul.
guide me