S
SinBin
It is my understanding that earned-value calculations only apply upto the
specified Status Date. My problem is that I have earned-values being
calculated and displayed on a tasks (which have %0 completed work) that start
AFTER the Status Date. This eventually causes problems because as work is
actually completed on such tasks the earned-value numbers are incorrect
because they include the values that were prematurely calculated. Has anyone
observed similar behaviour ? Is there some MS-Project setting I'm overlooking
that enforces earned-value calculation being cutoff at the Status Date ?
specified Status Date. My problem is that I have earned-values being
calculated and displayed on a tasks (which have %0 completed work) that start
AFTER the Status Date. This eventually causes problems because as work is
actually completed on such tasks the earned-value numbers are incorrect
because they include the values that were prematurely calculated. Has anyone
observed similar behaviour ? Is there some MS-Project setting I'm overlooking
that enforces earned-value calculation being cutoff at the Status Date ?