kippers
Hi,
I have a basic project plan for a project that I am working on- the only
resource allocated is myself. I have added timescales indicative of 'effort'
rather than 'elapsed' time. I now want to add myself as a resource, but show
70% utilisation to reflect my time dedicated (as effort) to the project.
However, when I add myself as a resource on the top line of the project, the
end date of the project remains the same- I expected it to be slightly later,
reflecting my 70% productivity rate....any ideas??