V
Vinayak Bhat
Hello
I am using MS Project 2003. I find that Effort driven, Fixed Units task
type is same as Fixed Work; please clarify.
The following is my observation.
Effort driven is OFF:
Task Type: Fixed Duration or Fixed Units: adding additional resources,
increases work, removing decreases the work.
Effort driven is ON:
(1) Task Type : Fixed Duration: adding additional resources decreases the
individual values for the resources.
(2)Task Type : Fixed Units: adding additional resources shortens the
duration of the task.
(3)Task Type : Fixed Work: adding additional resources shortens the duration
of the task.
Vinayak Bhat
PM@RCOM
I am using MS Project 2003. I find that Effort driven, Fixed Units task
type is same as Fixed Work; please clarify.
The following is my observation.
Effort driven is OFF:
Task Type: Fixed Duration or Fixed Units: adding additional resources,
increases work, removing decreases the work.
Effort driven is ON:
(1) Task Type : Fixed Duration: adding additional resources decreases the
individual values for the resources.
(2)Task Type : Fixed Units: adding additional resources shortens the
duration of the task.
(3)Task Type : Fixed Work: adding additional resources shortens the duration
of the task.
Vinayak Bhat
PM@RCOM