Hi,

I have a task in my project which I have tracked. The activity is 30%
complete and the client asks me to stop the work on that task. Kindly let me
know how do I treat this activity since I need to capture the effort of the
resources for the 30% work done.
 
G

Gérard Ducouret

Hi Sneha,
In the % Work Complete feld, enter 30%. Or, if the Work field value is
10days, enter 3d in the Actual Work field. Then set the Remaining Work to
zero.
Hope this helps,
Gérard Ducouret
 