Hi,
I have a task in my project which I have tracked. The activity is 30%
complete and the client asks me to stop the work on that task. Kindly let me
know how do I treat this activity since I need to capture the effort of the
resources for the 30% work done.
I have a task in my project which I have tracked. The activity is 30%
complete and the client asks me to stop the work on that task. Kindly let me
know how do I treat this activity since I need to capture the effort of the
resources for the 30% work done.