HelenaD
I work in a project where you want to enter calender time for a task e.g. a
task will need 12 weeks of calender time to be finished. If I enter 12 weeks
in the duration field I get 12 working weeks and NOT 12 calender weeks. If I
use start and stop dates the duration filed shows number of working weeks and
not calender weeks. I am not using resourses (people) connected to the tasks
in this project. I just want to schedule the tasks according to the calender.
How can I do this?
task will need 12 weeks of calender time to be finished. If I enter 12 weeks
in the duration field I get 12 working weeks and NOT 12 calender weeks. If I
use start and stop dates the duration filed shows number of working weeks and
not calender weeks. I am not using resourses (people) connected to the tasks
in this project. I just want to schedule the tasks according to the calender.
How can I do this?