D
dougawells
Hi -
I have a person that we contract for the life of a year long project.
When we sign the contract with them at the beginning of the project,
they get 50% of their contract amount. Then, half way through they get
another 25%, then at the end, they get the remaining 25%.
When I enter them as a cost - it splits out the total cost of their
contract on a day by day basis for the life of the project. Is there a
way I can get it not to do that, and manually enter their dollar
amounts at the three dates in question, rather than have to go through
all those days on a long project and delete what was put in there?
Thanks
I have a person that we contract for the life of a year long project.
When we sign the contract with them at the beginning of the project,
they get 50% of their contract amount. Then, half way through they get
another 25%, then at the end, they get the remaining 25%.
When I enter them as a cost - it splits out the total cost of their
contract on a day by day basis for the life of the project. Is there a
way I can get it not to do that, and manually enter their dollar
amounts at the three dates in question, rather than have to go through
all those days on a long project and delete what was put in there?
Thanks