Hi Larry,
If you can insert a VBA macro in the VB Editor the following will help you
Set (for instance) cost rate table B's standard cost for each resource in
their Number1 field
Copy/Paste the following macro into a VBE module:
Sub ForLarry
dim Slave as resource
for each Slave in activeproject.resources
if not slave is nothing then
slave.costratetables("B").Payrates(1).StandardRate=slave.number1
end if
next slave
end sub
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
Larry N said:
We're using Project Pro 2003 and Project Server 2003. I need to enter
various rates in the cost tables for each employee. I know how to do it for
an individual (using Resource Information in the Task Usage view), but is
there a way I can edit (i.e. paste a column from a spreadsheet) ALL
resources at once for, let's say, table B? Changing one resource at a time
is painful. : (