You shouldn't enter ANYTHING in the Start column (or Finish column for that
matter). Doing so sets a "Start No Earlier Than..." constraint on the task,
it does NOT set the start date. While the field is not 'read only' so as to
allow the convenience of entering constraints in that manner where
constraints are warranted, for 99.99% of the tasks in a project you should
be letting Project do its job as a schedule creator and calculate those
dates for you. You can display week numbers in stead of dates if you wish
by c hanging the date format options but let Project freely calculate them
for you.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Norbert said:
Hi,
I would like to know how I can enter week numbers in the Start column in
stead of the standaard date format dd-mm-yy.
Thanks,
Norbert