Enterprise Resource Calendar

J

Jackie

We have an Enterprise Resource Calendar that we are
associating to all enterprise resources. On one particular
enterprise resource we need to change one day as a non-
working day (vacation day). We went into the enterprise
resource calendar as Administrator (has permission to edit
enterprise resource data) and opened this particular
resource and set the day to non-working time. When we
save/close the enterprise resource calendar, log out of
project and go back in, the resource's non-working day did
not save. This seems so simple, but isn't working.

Any suggestions greatly appreciate.
 