Enterprise Resource Leveling Problem

F

Frederic

Hello,

I am having problems leveling enterprise resources. I created a very simple
project to try to understand what is going wrong with 4 identical tasks (same
duration, work, etc..). I assigned an "entreprise resource" to the first 2
and a "local" (i.e. non-entreprise) resource to the last 2.

I then hit "level now" and the last 2 tasks are properly levelled whereas
the first two stay unchanged.

I really need to do optimisation at a project level (basically, i do not
care about overallocation at an entreprise level for now).

Anybody can help ?

Fred

PS: i looked at the thread " Resource Leveling Problems" with no luck.
 
D

Dale Howard [MVP]

Frederic --

Open the project in questino, apply the Resource Sheet view and look in the
Indicators column to the left of the names of the two enterprise resources
you mention. Is there a yellow indicator in the column? If so, hover your
mouse pointer over the indicators for each resource. What does the tooltip
say? Let us know, as your problem may have nothing to do with whether the
overallocated resources are enterprise or non-enterprise.
 