In the Resources Sheet of Project, create the new resource : "Server x" in
the Resource Name column. In the drop down list of the Calendar column,
select the 24h calendar.
As Gerarrd said - but note, the Server is a Work resource, not a material
resource. I meantion that because some people think "material" means
"inanimate." But that's not true. Material resources are used up and
incorporated into the delieverable. Your server isn't - it is performing
work that contributes to the task's deliverable, just like a person, but it
isn't used up in the process.