B
Bob
I am using Project 2007 and have a program where the product moves through
different stations on its path final completion that I would like to track
(electrical, mechanical, coating, etc.). At each station there are various
staff members that will be used to complete that section of work. However
each time I imput the station as a resource, it counts it as an additional
staff member which throws off my costs and task hours. This is a similar
question to those asking about assigning equipment as a resource that I saw
on the post page. Has anything been done or discovered that would allow me
to track the stations of the program. I want to show on a high level how the
product moves throughout the stations (not just those individual staff
members that work on it).
different stations on its path final completion that I would like to track
(electrical, mechanical, coating, etc.). At each station there are various
staff members that will be used to complete that section of work. However
each time I imput the station as a resource, it counts it as an additional
staff member which throws off my costs and task hours. This is a similar
question to those asking about assigning equipment as a resource that I saw
on the post page. Has anything been done or discovered that would allow me
to track the stations of the program. I want to show on a high level how the
product moves throughout the stations (not just those individual staff
members that work on it).