Richard Courtney
If a project manager accepts updates from more than on
project, they get the message "Some approved task changes
cannot be updated in Microsoft Project files. Click view
details for more information. If you rejected a task, the
resource has been notified by e-mail. Please save your
Microsoft Project files with the new updates. The updated
tasks will remain in the table until you save the project
files."
After clicking View Details, you see a box with the
message "1.Project Name: Unknown error" and updates fail
for some of the tasks"
There seems to be a mixed set of symptoms here (sometimes
PM has updates accepted from more than one project,
sometimes accepted from only one project). A possible
factor (underline possible) is that some users actually
enter 0 in actual hours if they haven't done any work.
Does anyone know if this may be related to this problem,
or have you experienced problems with users entering 0 in
actual hours?
Thank you for any help you may be able to provide.
project, they get the message "Some approved task changes
cannot be updated in Microsoft Project files. Click view
details for more information. If you rejected a task, the
resource has been notified by e-mail. Please save your
Microsoft Project files with the new updates. The updated
tasks will remain in the table until you save the project
files."
After clicking View Details, you see a box with the
message "1.Project Name: Unknown error" and updates fail
for some of the tasks"
There seems to be a mixed set of symptoms here (sometimes
PM has updates accepted from more than one project,
sometimes accepted from only one project). A possible
factor (underline possible) is that some users actually
enter 0 in actual hours if they haven't done any work.
Does anyone know if this may be related to this problem,
or have you experienced problems with users entering 0 in
actual hours?
Thank you for any help you may be able to provide.