I have a relatively simple project defined with tasks and durations. I added
a few resources and reviewed the resulting schedule. The schedule that
Project computed had some unexplainable delays between tasks. The resource
assigned was not assigned anywhere else. By removing predecessor assignments
and then re-entering them, I have eliminated some of the gaps. However, this
approach is not very elegant. I'm concerned that when I add more complex
resource assignments, that I won't be able to find the unnecessary gaps. Can
someone shed some light on this issue?
Note: I do not use lags or leads in this part of the project.
Newbie JMJMJM
a few resources and reviewed the resulting schedule. The schedule that
Project computed had some unexplainable delays between tasks. The resource
assigned was not assigned anywhere else. By removing predecessor assignments
and then re-entering them, I have eliminated some of the gaps. However, this
approach is not very elegant. I'm concerned that when I add more complex
resource assignments, that I won't be able to find the unnecessary gaps. Can
someone shed some light on this issue?
Note: I do not use lags or leads in this part of the project.