Hello Gérard,
Thank you very much for the help.
Assigning the resources with proper percentages to start with, does
indeed give correct duration. However, reducing a resource to 75% from
100% is what actually happened to my project in real life, and I
could only get another one for two hours (25%), so that adjustment
had to be made.
Actually it is much more complicated than that. I have a project with
ten people and a list of tasks where the amount of work can be fixed.
There are also others with fixed duration. Some of the 10 people
only work part time. Two are only available for a limited time.
I have to find a way to distribute my resources in the optimal way,
(while respecting all other constraints), and that can only be done through
"playing" with the assignments, e.g. shuffling and increasing/decreasing
some
of them and seeing its effect on the rest.
I "played" for a while like this, and my project which initially lasted
two months, now ends in February 2005!
| Hello Jerry,
| Project works fine :
| - Set the work column for that fixed-work task to 16h.
| - Assign the first resource with units = 0,75 or 75%
| - Assign the second resource with units = 0,25 or 25%
|
| Never assign a resource withe the 100% default assignment units, expecting
| to correct it at 25% for ex. the Duration'll jump !
|
| Hope this helps,
|
| Gérard Ducouret [Project MVP]
| PragamaSoft ® - Paris
|
| "Jerry" <
[email protected]> a écrit dans le message de
| | > I am new to Project, and it might be my lack of knowledge, but:
| >
| > If I have a task (fixed work, effort driven) of 16 hours work, and
assign
| > 1 person 100%, MS Project correctly calculates duration of 2 days.
| > If I add a second person at 100%, duration is (correctly) set to one
day.
| > But if I assign first person 75%, and the other 25%, the duration
| > is 4 days! Should be 2, shouldn't it? A bug?
| >
| >
|
|