C
Cole
I don't think Project does this but I'll ask anyway,
If you have a task for 5 days; 40 hours; 1 Resource - at the end of 3
days if the task is 25% Complete (not physical % complete) will project
automatically adjust the duration to accomidate the extra time needed
to complete the task (reaching 100% complete)?
I think you have to do this manually, but a coworker believes the gods
of Microsoft 'had' to enable this as feature. LOL.
Thoughts?
If you have a task for 5 days; 40 hours; 1 Resource - at the end of 3
days if the task is 25% Complete (not physical % complete) will project
automatically adjust the duration to accomidate the extra time needed
to complete the task (reaching 100% complete)?
I think you have to do this manually, but a coworker believes the gods
of Microsoft 'had' to enable this as feature. LOL.
Thoughts?