J
jstern
I am seeing that anytime a task is running ahead of schedule the BCWP (EV)
and ACWP (AC) values seem to hit an upper limit of BCWS (PV) and the SPI and
CPI do not calculate correctly. If you lower the % complete below what was
scheduled, BCWP, ACWP, SPI, and CPI all calculate correctly.
I am working in a two-task test project where the resource has a $1/hr rate
for standard and overtime.
Am I doing something wrong, is there a problem with Project, or is this how
Project is supposed to work? If the last then can you explain why?
and ACWP (AC) values seem to hit an upper limit of BCWS (PV) and the SPI and
CPI do not calculate correctly. If you lower the % complete below what was
scheduled, BCWP, ACWP, SPI, and CPI all calculate correctly.
I am working in a two-task test project where the resource has a $1/hr rate
for standard and overtime.
Am I doing something wrong, is there a problem with Project, or is this how
Project is supposed to work? If the last then can you explain why?