even and uneven weekcalendar

S

sybmathics

Hi,

Is it possible to hava a customized calendar for even/uneven weeks.
For instance, every second week a non-working friday?

any help is greatly appreciated

sybmathics
 
M

Mike Glen

Hi sybmathics ,

Welcome to this Microsoft Project newsgroup :)

Yes, but you'll have to enter the data by hand for each week. Tools/Change
Working Time.../ use Control-click to select the 2 Fridays in that month
and, on the right, select the Nonworking time radio button. Repeat for each
month.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
S

sybmathics

Mike Glen said:
Hi sybmathics ,

Yes, but you'll have to enter the data by hand for each week.
Tools/Change Working Time.../ use Control-click to select the 2 Fridays in
that month and, on the right, select the Nonworking time radio button.
Repeat for each month.

Glen,
What I was looking for is a formula or function that creates an automatic
schedule for each week and second week.
I understand there is such a function in the outlook calendar. Can I perhaps
import the outlook calendar into Project?

Any suggestions?

Sybmathics
 
M

Mike Glen

Not that I know of, sorry :(

You could try posting on the developer newsgroup. Please see FAQ Item: 24.
Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 