I have several tasks on my project schedule that have negative Schedule
Variances, even though they haven't started yet.
Here's a simple example:
Status Date = 2/28/09
A task set to start on 3/3 with a duration of 1 day, assigned to a resource
that is allocated at 80%. PV = $148.53, EAC = $600, and SV = ($148.53).
Why is the SV negative?
I've read lots of EVM/MS-Project material, and have found nothing that would
explain this.
Help.
Thanks!
Joe Palm, PMP
Oshkosh, WI
(e-mail address removed)