D
Dan McCarty
I have a serious problem with Project. I've tried this on two
different PC's, both running Win2K and Project 2003. Either I don't
understand how it works or Project is just flat-out lying to me about
tasks. Here are some steps to easily reproduce this problem:
1. Start a new project file
2. Create a new task. Mine is called "test task."
3. Set the duration to 5d. Set the resource to "Bob."
4. Make sure that the tasks is set to 5d. Go to View...Task Usage to
see that Bob is working five 8-hour days.
5. Go back to the Gantt chart view and double click the task. In the
Resources tab, add Mary and set both Bob and Mary's units to 50%.
Click OK.
6. Now notice that instead of taking the same time to finish the task
(2 people at 50% vs. 1 at 100%), Project now says that the task will
take 6.67 days. In the Task Usage screen, Bob has been given twice as
much work as Mary!
Even worse, reducing the number of days back to 5 assigns Bob 20 hours
on the task and leaves Mary with just 13.33. So while Project is
reporting on the Gantt chart that it's a 40-hour task, only 33.3 hours
are being allocated to it!
So what's going on here?
different PC's, both running Win2K and Project 2003. Either I don't
understand how it works or Project is just flat-out lying to me about
tasks. Here are some steps to easily reproduce this problem:
1. Start a new project file
2. Create a new task. Mine is called "test task."
3. Set the duration to 5d. Set the resource to "Bob."
4. Make sure that the tasks is set to 5d. Go to View...Task Usage to
see that Bob is working five 8-hour days.
5. Go back to the Gantt chart view and double click the task. In the
Resources tab, add Mary and set both Bob and Mary's units to 50%.
Click OK.
6. Now notice that instead of taking the same time to finish the task
(2 people at 50% vs. 1 at 100%), Project now says that the task will
take 6.67 days. In the Task Usage screen, Bob has been given twice as
much work as Mary!
Even worse, reducing the number of days back to 5 assigns Bob 20 hours
on the task and leaves Mary with just 13.33. So while Project is
reporting on the Gantt chart that it's a 40-hour task, only 33.3 hours
are being allocated to it!
So what's going on here?